LU Ru,JU Zhi jian,DU Qiong.Upgrading and Reconstruction Project Design of Wastewater Treatment Plant with A/O Process[J].China Water & Wastewater,2018,34(20):56-59.
采用A/O工艺的污水处理厂提标改造工程设计
- Title:
- Upgrading and Reconstruction Project Design of Wastewater Treatment Plant with A/O Process
- 文章编号:
- 1000-4602(2018)20-0056-04
- 分类号:
- TU992.3
- 文献标志码:
- C
- 摘要:
- 辽宁省某污水处理厂设计规模为10×104 m3/d,采用A/O处理工艺。升级改造工程要求设计出水水质从《城镇污水处理厂污染物排放标准》(GB 18918—2002)一级B标准提升至一级A标准。针对出水总氮超标问题,增设一组A/O生化池,以降低脱氮负荷,同时增设碳源投加系统,从而保证了脱氮效率;针对进水含砂量大,导致粗、细格栅和提升水泵等机械设备磨损严重的问题,提标改造中增设了粗格栅及平流沉砂池,使进水中的砂在平流沉砂池内预沉,同时去除大颗粒漂浮物,从而保证了粗、细格栅及提升泵的正常运行。实际运行表明,提标改造工程出水水质完全达到一级A标准。
- Abstract:
- A/O process was adopted in a wastewater treatment plant with capacity of 10×104 m3/d in Liaoning Province. The effluent quality of reconstruction project was required to be upgraded from the first level B standard to the first level A criteria specified in the Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant (GB 18918-2002). Denitrifying load would be lowered by construction of a new A/O biochemical tank, and nitrogen removal efficiency would be ensured by supplement of carbon source. The inlet water contained a lot of grit which led to serious wear of mechanical equipment such as coarse screen, fine rack and lift pumps. The grit and large particles of floatation in water would be settled by usage of the coarse screen and the horizontal flow grid chamber. As a result, the coarse screen, fine rack and lift pumps would operate normally. Actual operation showed the effluent quality could meet the first level A standard.
参考文献/References:
[1]周雹. 活性污泥工艺简明原理及设计计算[M]. 北京:中国建筑工业出版社,2005.Zhou Bao. Simple Principle and Design Calculation of Activated Sludge Process[M]. Beijing:China Architecture & Building Press,2005(in Chinese).
[2]周丹,周雹. 污水脱氮工艺中外部碳源投加量简易计算方法[J]. 给水排水,2011,37(11):38-41.Zhou Dan,Zhou Bao. Simple calculation method for the outside carbon source dosage for nitrogen removal process in wastewater treatment[J]. Water & Wastewater Engineering,2011,37(11):38-41(in Chinese).
[3]孙淑琴,常华,李建科,等. 水厂改造工程设计与运行案例分析[J]. 净水技术,2013,32(4):90-95.Sun Shuqin,Chang Hua,Li Jianke,et al. Case analysis of design and operation for rehabilitation project of water treatment plant[J]. Water Purification Technology,2013,32(4):90-95(in Chinese).
相似文献/References:
[1]张莹,王昌稳,李军,等.投加微粉强化低浓度生活污水活性污泥好氧颗粒化[J].中国给水排水,2018,34(21):12.
ZHANG Ying,WANG Chang wen,LI Jun,et al.Strengthening Aerobic Granulation of Activated Sludge by Adding Micro Powder in Low Concentration Sewage Treatment[J].China Water & Wastewater,2018,34(20):12.
[2]熊建英.MBBR+磁混凝工艺用于污水处理厂提标改造[J].中国给水排水,2018,34(20):50.
XIONG Jian ying.Application of MBBR + Magnetic Coagulation Process for Upgrading of Wastewater Treatment Plant[J].China Water & Wastewater,2018,34(20):50.
[3]王连杰,李金河,郑兴灿,等.城镇污水系统中病毒特性和规律相关研究分析[J].中国给水排水,2020,36(6):14.
[4]周亚梁,黄东月.南方某污水处理厂提标改造工艺运行优化[J].中国给水排水,2020,36(8):113.
[5]顾玉中,黄学军,金秋景,等.污水处理厂轴流泵电流爬升的原因及解决方法[J].中国给水排水,2020,36(10):119.
[6]王凯,高波,张磊,等.危废处置中心污水分质处理工艺设计及运行经验[J].中国给水排水,2020,36(16):69.
WANG Kai,GAO Bo,ZHANG Lei,et al.Experience in Design and Operation of Wastewater Separate Treatment in the Hazardous Waste Disposal Center[J].China Water & Wastewater,2020,36(20):69.
[7]李爽,王向阳,郝晓地,等.全生命周期评价在污水处理中的研究与应用[J].中国给水排水,2020,36(18):32.
LI Shuang,WANG Xiang-yang,HAO Xiao-di,et al.Research and Application of Life Cycle Assessment in Wastewater Treatment[J].China Water & Wastewater,2020,36(20):32.
[8]许晓明,刘宇心,闫萍,等.以工业废水为主的污水厂准Ⅳ类水质提标扩建工程设计[J].中国给水排水,2020,36(18):60.
XU Xiao-ming,LIU Yu xin,YAN Ping,et al.A Design Case of Upgrading and Expansion Project to Meet the Quasi-Ⅳ Class Standard in a WWTP with Industrial Wastewater as Its Major Influent[J].China Water & Wastewater,2020,36(20):60.
[9]聂健锋,曾超.三峡库区Carrousel氧化沟工艺提标升级改造设计[J].中国给水排水,2020,36(18):66.
NIE Jian-feng,ZENG Chao.Design of Upgrading and Reconstruction of Carrousel Oxidation Ditch Process in Three Gorges Reservoir Area[J].China Water & Wastewater,2020,36(20):66.
[10]张莉,余国富,瞿露,等.重庆市某污水处理厂一级A提标改造运行效果分析[J].中国给水排水,2020,36(18):95.
ZHANG Li,YU Guo-fu,QU Lu,et al.Analysis on the Operation Effect of a WWTP Upgrading Project for the Firstlevel A Standard in Chongqing[J].China Water & Wastewater,2020,36(20):95.
[11]张岳,葛铜岗,孙永利,等.基于城镇污水处理全流程环节的碳排放模型研究[J].中国给水排水,2021,37(9):65.
ZHANG Yue,GE Tong-gang,SUN Yong-li,et al.Research on Carbon Emission Model Based on the Whole Process of Urban Sewage Treatment[J].China Water & Wastewater,2021,37(20):65.
备注/Memo
作者简介:卢如(1987-),女,江西丰城人,硕士,工程师,主要从事市政给排水处理研究。
E-mail:303632669@qq.com
收稿日期:2018-04-18