YAN Ying-ying,MENG Chun-lin,LIANG Yuan,et al.Continuous Deep Dewatering Coupled with Low Temperature Drying Process in Yingtan Sludge Treatment Plant[J].China Water & Wastewater,2020,36(16):105-110.
连续深度脱水耦合低温干化工艺用于鹰潭污泥处理厂
- Title:
- Continuous Deep Dewatering Coupled with Low Temperature Drying Process in Yingtan Sludge Treatment Plant
- Keywords:
- sludge treatment; deep dewatering; low temperature drying
- 摘要:
- 鹰潭市污泥处理厂设计处理规模为65 t/d(污泥含水率为80%),采用连续深度脱水耦合低温干化两段式组合工艺。第一段是干化前的预脱水,利用高压带式压滤机将污泥含水率由80%降至65%~70%;第二段是污泥低温干化设备,采用对流热风干燥的方式对网带上的湿料污泥进行脱水干化减量至含水率为20%。实践表明,在低温干化工艺前端增加机械深度脱水段,可以降低整体的投资和运行成本。此外,两段式工艺提高了系统的灵活性及生产保障冗余度,干化污泥的处置出路近期为园林绿化肥料骨料,远期送至垃圾焚烧厂进行掺烧。该工程的成功运行实现了鹰潭市污泥的减量化和资源化,对城镇污水处理厂污泥处理处置工艺选择具有示范意义。
- Abstract:
- The combined two-stage process of continuous deep dewatering coupled with low temperature drying was adopted in Yingtan sludge treatment plant with the capability of 65 t/d (the sludge water content was 80%). In the first stage of pre-dewatering before drying, the high-pressure belt filter press was used to reduce the water content to 65%-70% from 80% by mechanical dewatering. In the second stage of low temperature drying equipment, the water content of the wet sludge was reduced to 20% by convection hot air drying. The practice showed that adding a mechanical deep dewatering section at the front of the low temperature drying process could reduce the overall investment and operating costs. Furthermore, the two-stage process could enhance the flexibility and production guarantee redundancy of the system, the treated sludge were used as aggregate of landscaping fertilizer and would be sent to waste incineration plant in the long term. The successful operation of the project has realized the reduction and resource utilization of sludge in Yingtan, which is of demonstration significance to the selection of sludge treatment and disposal process in municipal wastewater treatment plant.
相似文献/References:
[1]宋晓雅.小红门污泥热水解厌氧消化项目运行两周年之回顾[J].中国给水排水,2018,34(22):116.
SONG Xiao-ya.Review of Biennial Operation of Xiaohongmen Thermal Hydrolysis Anaerobic Digestion System[J].China Water & Wastewater,2018,34(16):116.
[2]仝恩从.保定市污泥处理中心项目的工艺选择及思考[J].中国给水排水,2018,34(20):21.
TONG En cong.Process Selection and Thought of Baoding Sludge Treatment Center Project[J].China Water & Wastewater,2018,34(16):21.
[3]林明,庄毅璇,李建,等.某污水处理厂污泥处理系统技术改造[J].中国给水排水,2018,34(20):109.
LIN Ming,ZHUANG Yi xuan,LI Jian,et al.Technological Transformation of Sludge Treatment System in a WWTP[J].China Water & Wastewater,2018,34(16):109.
[4]王首都,黄申斌,魏小玲,等.立式移动地板发酵仓技术在崇明某污水厂的应用[J].中国给水排水,2020,36(14):138.
WANG Shou-du,HUANG Shen-bin,WEI Xiao-ling,et al.Application of Vertical Mobile Floor Fermentation Bin in a Sewage Treatment Plant in Chongming District[J].China Water & Wastewater,2020,36(16):138.
[5]孙建升,叶雅丽,郑兴灿,等.昆明市污水处理厂污泥处理工艺的研究与探讨[J].中国给水排水,2020,36(18):108.
SUN Jian-sheng,YE Ya-li,ZHENG Xing-can,et al.Research and Discussion on the Sludge Disposal Technology of Kunming WWTPs[J].China Water & Wastewater,2020,36(16):108.
[6]卓星星,尹兴新,石烁辉,等.负荷对高盐污泥氧化硫硫杆菌调理系统脱水效能的影响[J].中国给水排水,2020,36(23):27.
ZHUO Xing-xing,YIN Xing-xin,SHI Shuo-hui,et al.Effect of Load on Dewatering Efficiency of High Salinity Sludge Conditioning System with Acidithiobacillus thiooxidans[J].China Water & Wastewater,2020,36(16):27.
[7]胡佩佩,侯锋,范莹,等.深度脱水污泥好氧发酵工艺研究[J].中国给水排水,2021,37(17):74.
HU Pei-pei,HOU Feng,FAN Ying,et al.Aerobic Fermentation Process of Deep Dewatering Sludge[J].China Water & Wastewater,2021,37(16):74.
[8]王声东.老港垃圾渗滤液应急项目污泥深度脱水工程实例[J].中国给水排水,2021,37(24):107.
WANG Sheng-dong.A Case of Sludge Deep Dewatering in Laogang Landfill Leachate Emergency Treatment Project[J].China Water & Wastewater,2021,37(16):107.
[9]孟继安,钟达文,孙昊,等.SEUE-WAO污泥湿式氧化工艺的生产性试验研究[J].中国给水排水,2023,39(15):1.
MENGJi-an,ZHONGDa-wen,SUNHao,et al.Full-scale Study on SEUE-WAO Sludge Wet Air Oxidation Process[J].China Water & Wastewater,2023,39(16):1.
[10]王倩,吴雪松,李伟,等.北排清河二厂污泥脱水工艺节能降耗优化运行策略[J].中国给水排水,2024,40(2):94.
WANGQian,WUXue-song,LIWei,et al.Optimized Operation Strategy for Energy Saving and Consumption Reduction of Sludge Dewatering Process in Qinghe Ⅱ Reclaimed Water Plant of Beijing Drainage Group[J].China Water & Wastewater,2024,40(16):94.