WANG Zheng-fa,SHENTU Jun-jie,CAI Peng-xiang.Design of MBBR/DBDF Process for Quasi-Ⅳ Upgrading and Reconstruction of a Wastewater Treatment Plant in Zhejiang[J].China Water & Wastewater,2021,37(20):61-65.
浙江某污水厂准Ⅳ类提标改造MBBR+DBDF工艺设计
- Title:
- Design of MBBR/DBDF Process for Quasi-Ⅳ Upgrading and Reconstruction of a Wastewater Treatment Plant in Zhejiang
- 关键词:
- 提标改造; A/A/O+MBBR+DBDF工艺; 工程效果
- 摘要:
- 浙江某城市污水处理厂总规模8.0×104 m3/d,分三期建设,其中一、二期共4.0×104 m3/d,主体工艺为改良式SBR工艺,出水执行《城镇污水处理厂污染物排放标准》(GB 18918—2002)一级B标准。本次提标改造要求出水达到浙江省地方标准《城镇污水处理厂主要水污染物排放标准》(DB 33/2169—2018)。针对厂区可用土地少、改造时间短的特点,提标改造工程采用A/A/O+MBBR+DBDF(反硝化深床滤池)组合工艺。改造完成后,污水厂运行稳定,各项出水指标均达到设计标准。
- Abstract:
- The total scale of a municipal wastewater treatment plant in Zhejiang Province is 8.0 ×104 m3/d, which is divided into three phases, of which the first and the second phases are 4.0×104 m3/d. The main process is modified SBR process, and the effluent quality was required to meet the first level B criteria specified in Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant (GB 18918-2002). However, the discharge standard is required to upgrade to the local standard of Zhejiang Province Discharge Standard of Major Water Pollutants for Municipal Wastewater Treatment Plant (DB 33/2169-2018). Owing to the limited footprint and short construction term, the combined process of A/A/O, MBBR and DBDF was finally adopted in the upgrading project. The wastewater treatment plant runs stably after the reconstruction, and all indexes in the effluent reach the design standards.
相似文献/References:
[1]熊建英.MBBR+磁混凝工艺用于污水处理厂提标改造[J].中国给水排水,2018,34(20):50.
XIONG Jian ying.Application of MBBR + Magnetic Coagulation Process for Upgrading of Wastewater Treatment Plant[J].China Water & Wastewater,2018,34(20):50.
[2]卢如,巨志剑,杜琼.采用A/O工艺的污水处理厂提标改造工程设计[J].中国给水排水,2018,34(20):56.
LU Ru,JU Zhi jian,DU Qiong.Upgrading and Reconstruction Project Design of Wastewater Treatment Plant with A/O Process[J].China Water & Wastewater,2018,34(20):56.
[3]周亚梁,黄东月.南方某污水处理厂提标改造工艺运行优化[J].中国给水排水,2020,36(8):113.
[4]许晓明,刘宇心,闫萍,等.以工业废水为主的污水厂准Ⅳ类水质提标扩建工程设计[J].中国给水排水,2020,36(18):60.
XU Xiao-ming,LIU Yu xin,YAN Ping,et al.A Design Case of Upgrading and Expansion Project to Meet the Quasi-Ⅳ Class Standard in a WWTP with Industrial Wastewater as Its Major Influent[J].China Water & Wastewater,2020,36(20):60.
[5]聂健锋,曾超.三峡库区Carrousel氧化沟工艺提标升级改造设计[J].中国给水排水,2020,36(18):66.
NIE Jian-feng,ZENG Chao.Design of Upgrading and Reconstruction of Carrousel Oxidation Ditch Process in Three Gorges Reservoir Area[J].China Water & Wastewater,2020,36(20):66.
[6]张莉,余国富,瞿露,等.重庆市某污水处理厂一级A提标改造运行效果分析[J].中国给水排水,2020,36(18):95.
ZHANG Li,YU Guo-fu,QU Lu,et al.Analysis on the Operation Effect of a WWTP Upgrading Project for the Firstlevel A Standard in Chongqing[J].China Water & Wastewater,2020,36(20):95.
[7]马丽芳,陈菊香,孙锐.克拉玛依市某污水处理厂一级A提标改造工程实例[J].中国给水排水,2020,36(18):122.
MA Li-fang,CHEN Ju-xiang,SUN Rui.A WWTP Upgrading Reconstruction Project to Meet the First Level A Discharge Standard in Karamay[J].China Water & Wastewater,2020,36(20):122.
[8]孙高升,王东东,弋凡,等.淮河流域地表水类Ⅳ类标准污水深度处理工艺研究[J].中国给水排水,2020,36(19):16.
SUN Gao-sheng,WANG Dong-dong,YI Fan,et al.Advanced Wastewater Treatment Process with Effluent Quality Meeting Level Quasi Ⅳ Criteria of Surface Water in Huai River Basin[J].China Water & Wastewater,2020,36(20):16.
[9]李亮,邱宏俊.改良A2/O氧化沟强化生化处理技术用于污水厂提标改造[J].中国给水排水,2020,36(20):124.
LI Liang,QIU Hong-jun.Application of Improved A2/O Oxidation Ditch Enhanced Biochemical Treatment Process for Upgrading the Wastewater Treatment Plant[J].China Water & Wastewater,2020,36(20):124.
[10]黄志心.城镇污水处理厂提标改造实践与思考[J].中国给水排水,2020,36(22):48.
HUANG Zhi-xin.Practice and Thinking of Upgrading and Reconstruction of Municipal Wastewater Treatment Plant[J].China Water & Wastewater,2020,36(20):48.