MOWen-ting,YANGTao,GUOJun.Upgrading Scheme and Project Design of a WWTP for Quasi-level Ⅲ Surface Water Criteria[J].China Water & Wastewater,2022,38(20):90-95.
污水厂地表水准Ⅲ类标准提标改造方案和工程设计
- Title:
- Upgrading Scheme and Project Design of a WWTP for Quasi-level Ⅲ Surface Water Criteria
- Keywords:
- upgrading and reconstruction; denitrification deep-bed filter; three-step ozone catalytic oxidation; dissolved air flotation
- 摘要:
- 武汉某污水处理厂现状出水水质执行一级A标准,提标改造工程要求出水水质执行地表水准Ⅲ类标准(TN≤6 mg/L)。根据现状处理效果分析,提标改造工程的处理难点是TN、COD和TP的深度去除,需增加对应的专用深度处理单元。根据污染物去除机理和中试研究结果,深度脱氮单元采用反硝化深床滤池工艺,深度降解COD单元采用三级臭氧催化氧化工艺,深度除磷单元采用溶气气浮工艺。此外,通过中试确定了溶气气浮工艺的絮凝剂投加量和回流比、臭氧催化氧化工艺的O3消耗量与COD去除量的质量比以及催化剂填充高度。
- Abstract:
- The current effluent quality of a wastewater treatment plant (WWTP) in Wuhan implements with first level A discharge standard, which will be promoted to quasi-level Ⅲ criteria of surface water (TN≤6 mg/L) in its upgrading and reconstruction project. Based on the analysis of current treatment effect, further removal of TN, COD and TP is regarded as the difficulty of the project and the correspondingly special advanced treatment process shall be supplemented. According to the results of the mechanism analysis for pollutants removal and the pilot study, denitrification deep-bed filter, three-step ozone catalytic oxidation and dissolved air flotation are selected for the further removal of TN, COD and TP, respectively. Besides, the flocculant dosage and reflux ratio of dissolved air flotation, the mass ratio of O3 consumption to COD removal and loading height of catalyst bed in ozone catalytic oxidation are determined based on the results of pilot study.
相似文献/References:
[1]熊建英.MBBR+磁混凝工艺用于污水处理厂提标改造[J].中国给水排水,2018,34(20):50.
XIONG Jian ying.Application of MBBR + Magnetic Coagulation Process for Upgrading of Wastewater Treatment Plant[J].China Water & Wastewater,2018,34(20):50.
[2]卢如,巨志剑,杜琼.采用A/O工艺的污水处理厂提标改造工程设计[J].中国给水排水,2018,34(20):56.
LU Ru,JU Zhi jian,DU Qiong.Upgrading and Reconstruction Project Design of Wastewater Treatment Plant with A/O Process[J].China Water & Wastewater,2018,34(20):56.
[3]周亚梁,黄东月.南方某污水处理厂提标改造工艺运行优化[J].中国给水排水,2020,36(8):113.
[4]许晓明,刘宇心,闫萍,等.以工业废水为主的污水厂准Ⅳ类水质提标扩建工程设计[J].中国给水排水,2020,36(18):60.
XU Xiao-ming,LIU Yu xin,YAN Ping,et al.A Design Case of Upgrading and Expansion Project to Meet the Quasi-Ⅳ Class Standard in a WWTP with Industrial Wastewater as Its Major Influent[J].China Water & Wastewater,2020,36(20):60.
[5]聂健锋,曾超.三峡库区Carrousel氧化沟工艺提标升级改造设计[J].中国给水排水,2020,36(18):66.
NIE Jian-feng,ZENG Chao.Design of Upgrading and Reconstruction of Carrousel Oxidation Ditch Process in Three Gorges Reservoir Area[J].China Water & Wastewater,2020,36(20):66.
[6]张莉,余国富,瞿露,等.重庆市某污水处理厂一级A提标改造运行效果分析[J].中国给水排水,2020,36(18):95.
ZHANG Li,YU Guo-fu,QU Lu,et al.Analysis on the Operation Effect of a WWTP Upgrading Project for the Firstlevel A Standard in Chongqing[J].China Water & Wastewater,2020,36(20):95.
[7]马丽芳,陈菊香,孙锐.克拉玛依市某污水处理厂一级A提标改造工程实例[J].中国给水排水,2020,36(18):122.
MA Li-fang,CHEN Ju-xiang,SUN Rui.A WWTP Upgrading Reconstruction Project to Meet the First Level A Discharge Standard in Karamay[J].China Water & Wastewater,2020,36(20):122.
[8]孙高升,王东东,弋凡,等.淮河流域地表水类Ⅳ类标准污水深度处理工艺研究[J].中国给水排水,2020,36(19):16.
SUN Gao-sheng,WANG Dong-dong,YI Fan,et al.Advanced Wastewater Treatment Process with Effluent Quality Meeting Level Quasi Ⅳ Criteria of Surface Water in Huai River Basin[J].China Water & Wastewater,2020,36(20):16.
[9]李亮,邱宏俊.改良A2/O氧化沟强化生化处理技术用于污水厂提标改造[J].中国给水排水,2020,36(20):124.
LI Liang,QIU Hong-jun.Application of Improved A2/O Oxidation Ditch Enhanced Biochemical Treatment Process for Upgrading the Wastewater Treatment Plant[J].China Water & Wastewater,2020,36(20):124.
[10]黄志心.城镇污水处理厂提标改造实践与思考[J].中国给水排水,2020,36(22):48.
HUANG Zhi-xin.Practice and Thinking of Upgrading and Reconstruction of Municipal Wastewater Treatment Plant[J].China Water & Wastewater,2020,36(20):48.