SHENHao,YANGZhong-qi,WANGFan,et al.Application of MBBR and Magnetic Coagulation Precipitation Process in Retrofitting of a WWTP with Limited Construction Land[J].China Water & Wastewater,2023,39(8):112-119.
MBBR+磁混凝沉淀工艺用于用地受限污水厂改造
- Title:
- Application of MBBR and Magnetic Coagulation Precipitation Process in Retrofitting of a WWTP with Limited Construction Land
- Keywords:
- MBBR; magnetic coagulation precipitation process; upgrading and retrofitting; nitrogen and phosphorus removal
- 摘要:
- 广东省某污水处理厂处理规模为12×104 m3/d,设计出水水质要求达到广东省《水污染物排放限值》(DB 44/26—2001)第二时段一级标准和国家《城镇污水处理厂污染物排放标准》(GB 18918—2002)一级A标准中的较严值。该污水处理厂提标面临占地受限问题。该项目采用MBBR+磁混凝沉淀工艺,紧密结合现状工艺设施对原有A2/O工艺进行改造。生化池原位镶嵌MBBR工艺,无需新建构筑物。深度处理单元采用磁混凝沉淀工艺,在极小占地条件下完成实施,保证了SS和TP的高效稳定去除。改造后出水COD为(15.95±4.16) mg/L、BOD5为(4.97±1.40) mg/L、SS为(7.10±1.68) mg/L、TN为(10.29±2.59) mg/L、TP为(0.17±0.11) mg/L、NH3-N为(1.24±1.17) mg/L,出水水质稳定优于设计出水标准。实践证明,MBBR+磁混凝沉淀工艺具有简洁集约、稳定高效的特点,适用于占地受限型污水处理厂的改扩建或新建。
- Abstract:
- A wastewater treatment plant (WWTP) in Guangdong Province with capacity of 12×104 m3/d, is required to meet the stricter values of first level criteria in the second period of Guangdong Province local Discharge Limits of Water Pollutants (DB 44/26-2001) and of first level A criteria in Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant (GB 18918-2002). The retrofitting of the WWTP was facing the problem of limited land occupation. The MBBR and magnetic coagulation precipitation process is selected to retrofit the original A2/O process in close combination with the current process facilities. The biochemical tank is embedded with MBBR process in?situ without the need for new construction. In order to ensure the efficient and stable removal of SS and TP, magnetic coagulation precipitation process is adopted in advanced treatment unit to construct with minimal land occupation. After retrofitting, the effluent COD is (15.95±4.16) mg/L, BOD5 is (4.97±1.40) mg/L, SS is (7.10±1.68) mg/L, TN is (10.29±2.59) mg/L, TP is (0.17±0.11) mg/L and NH3-N is (1.24±1.17) mg/L, which are stable and superior to the design effluent standard. The practice shows that the MBBR and magnetic coagulation precipitation process is simple, intensive, stable and efficient, which is applicable to the retrofitting, expansion or new construction of WWTP with limited land occupation.
相似文献/References:
[1]朱点钰,陈年浩,朱津苇,等.填料类型对MBBR启动及运行效能的影响[J].中国给水排水,2018,34(21):1.
ZHU Dian yu,CHEN Nian hao,ZHU Jin wei,et al.Effect of Carrier Type on Startup and Operating Efficiency of Moving Bed Biofilm Reactor[J].China Water & Wastewater,2018,34(8):1.
[2]郑临奥,吴迪,张晶晶,等.城市污水泵站改为河道生态补给站的实践总结[J].中国给水排水,2018,34(20):82.
ZHENG Lin ao,WU Di,ZHANG Jing jing,et al.Practice of River Ecological Replenishment Retrofitting from an Urban Sewage Pumping Station[J].China Water & Wastewater,2018,34(8):82.
[3]郭莉芳,朱宇峰,滕良方,等.MBBR用于南方某污水厂强化脱氮效果分析[J].中国给水排水,2020,36(7):101.
[4]周家中,吴迪,郑临奥.纯膜MBBR工艺在国内外的工程应用[J].中国给水排水,2020,36(22):37.
ZHOU Jia-zhong,WU Di,ZHENG Lin-ao.Engineering Application of Pure MBBR Process at Home and Abroad[J].China Water & Wastewater,2020,36(8):37.
[5]杨平,周家中,管勇杰,等.基于MBBR的AAO和Bardenpho工艺改造效果对比[J].中国给水排水,2021,37(7):11.
YANG Ping,ZHOU Jia-zhong,GUAN Yong-jie,et al.Comparison of AAO and Bardenpho Processes Transformation Effect Based on MBBR[J].China Water & Wastewater,2021,37(8):11.
[6]孙庆花,张晓霞,赵益华,等.天津某高盐高排放标准污水厂提标改造工程设计[J].中国给水排水,2021,37(8):83.
SUN Qing-hua,ZHANG Xiao-xia,ZHAO Yi-hua,et al.Design of a Wastewater Treatment Plant Upgrading Project with High Salinity Influent and High Discharge Standard in Tianjin[J].China Water & Wastewater,2021,37(8):83.
[7]周家中,宋平周,张爽,等.占地受限下北方某高标准新建污水厂工程设计[J].中国给水排水,2021,37(12):76.
ZHOU Jia-zhong,SONG Ping-zhou,ZHANG Shuang,et al.Engineering Design of a New High-standard Wastewater Treatment Plant with Limited Footprint Area in North China[J].China Water & Wastewater,2021,37(8):76.
[8]陈如勇,张晓霞,周家中,等.MSBR改为三级A/O-MBBR连续流工艺的应用效果[J].中国给水排水,2021,37(14):108.
CHEN Ru-yong,ZHANG Xiao-xia,ZHOU Jia-zhong,et al.Practical Application Effect of Retrofitted MSBR into Three-stage A/O-MBBR Continuous Flow Process[J].China Water & Wastewater,2021,37(8):108.
[9]王雪欣,毕学军,麻弛张,等.两点进水三段A/O-MBBR生物脱氮中试研究[J].中国给水排水,2021,37(17):62.
WANG Xue-xin,BI Xue-jun,MA Chi-zhang,et al.Nitrogen Removal of Pilot-scale Three Stages A/O-MBBR with Two-step-feed[J].China Water & Wastewater,2021,37(8):62.
[10]周小琳,樊星,毕学军,等.两段式A/O-MBBR工艺生物脱氮中试与系统优化[J].中国给水排水,2021,37(19):72.
ZHOU Xiao-lin,FAN Xing,BI Xue-jun,et al.Pilot-scale Test and System Optimization of Two-stage A/O-MBBR Process for Biological Nitrogen Removal[J].China Water & Wastewater,2021,37(8):72.