XU Xiao-ming,LIU Yu xin,YAN Ping,et al.A Design Case of Upgrading and Expansion Project to Meet the Quasi-Ⅳ Class Standard in a WWTP with Industrial Wastewater as Its Major Influent[J].China Water & Wastewater,2020,36(18):60-65.
以工业废水为主的污水厂准Ⅳ类水质提标扩建工程设计
- Title:
- A Design Case of Upgrading and Expansion Project to Meet the Quasi-Ⅳ Class Standard in a WWTP with Industrial Wastewater as Its Major Influent
- Keywords:
- printing and dyeing wastewater; upgrading and reconstruction project; two-stage A/O process; Fenton; advanced treatment
- 摘要:
- 浙江某污水厂提标及扩建工程总规模为4×104 m3/d,其中提标2×104 m3/d、扩建2×104 m3/d。污水厂原采用厌氧水解+MSBR+絮凝沉淀池+V型滤池处理工艺,出水执行一级A排放标准,提标及扩建工程要求出水水质达到浙江省地方标准《城镇污水处理厂主要水污染物排放标准》(DB 33/2169—2018)中现有污水厂标准。针对进水中工业废水占比为60%、污染物浓度波动大、含难降解有机物等特点,扩建工程采用调节池+水解酸化池+二级A/O生化池+芬顿+高效沉淀池+V型滤池工艺。提标工程将原MSBR池改造为A/A/O池,并增加了芬顿深度处理工艺,改造了絮凝沉淀池,实际运行效果良好,出水水质完全达到设计目标,直接运行成本为1.42 元/m3。
- Abstract:
- The total scale of upgrading and expansion project in a wastewater plant in Zhejiang is 4×104 m3/d, including upgrading project of 2×104 m3/d and expansion project of 2×104 m3/d. The wastewater treatment plant originally adopted anaerobic hydrolysis+MSBR+flocculation sedimentation tank+V-type filter treatment process, the effluent carries out the first class A discharge standard. The upgrading and expansion project requires the effluent quality to meet the existing wastewater treatment plant standard in Zhejiang Province local standard Discharge Standard of Major Water Pollutants for Municipal Wastewater Treatment Plant (DB 33/2169-2018). According to the characteristics of 60% industrial wastewater in influent, large fluctuation of pollutant concentration and refractory organic matter, the process of regulating tank+hydrolysis acidification tank+two-stage A/O+Fenton+high efficiency sedimentation tank+V-type filter was adopted in the expansion project. The Fenton process was added, and MSBR was transformed into A/A/O tank, flocculation sedimentation tank was reformed in upgrading project. The actual operation effect was good, and the effluent quality reached the design goal completely, and the direct operating cost was 1.42 yuan/m3.
相似文献/References:
[1]熊建英.MBBR+磁混凝工艺用于污水处理厂提标改造[J].中国给水排水,2018,34(20):50.
XIONG Jian ying.Application of MBBR + Magnetic Coagulation Process for Upgrading of Wastewater Treatment Plant[J].China Water & Wastewater,2018,34(18):50.
[2]卢如,巨志剑,杜琼.采用A/O工艺的污水处理厂提标改造工程设计[J].中国给水排水,2018,34(20):56.
LU Ru,JU Zhi jian,DU Qiong.Upgrading and Reconstruction Project Design of Wastewater Treatment Plant with A/O Process[J].China Water & Wastewater,2018,34(18):56.
[3]周亚梁,黄东月.南方某污水处理厂提标改造工艺运行优化[J].中国给水排水,2020,36(8):113.
[4]赵健忠,王学华,王浩,等.浙江某印染废水处理工程改造及分析[J].中国给水排水,2020,36(14):134.
ZHAO Jian-zhong,WANG Xue-hua,WANG Hao,et al.Reconstruction and Analysis of a Printing and Dyeing Wastewater Treatment Project in Zhejiang[J].China Water & Wastewater,2020,36(18):134.
[5]聂健锋,曾超.三峡库区Carrousel氧化沟工艺提标升级改造设计[J].中国给水排水,2020,36(18):66.
NIE Jian-feng,ZENG Chao.Design of Upgrading and Reconstruction of Carrousel Oxidation Ditch Process in Three Gorges Reservoir Area[J].China Water & Wastewater,2020,36(18):66.
[6]张莉,余国富,瞿露,等.重庆市某污水处理厂一级A提标改造运行效果分析[J].中国给水排水,2020,36(18):95.
ZHANG Li,YU Guo-fu,QU Lu,et al.Analysis on the Operation Effect of a WWTP Upgrading Project for the Firstlevel A Standard in Chongqing[J].China Water & Wastewater,2020,36(18):95.
[7]马丽芳,陈菊香,孙锐.克拉玛依市某污水处理厂一级A提标改造工程实例[J].中国给水排水,2020,36(18):122.
MA Li-fang,CHEN Ju-xiang,SUN Rui.A WWTP Upgrading Reconstruction Project to Meet the First Level A Discharge Standard in Karamay[J].China Water & Wastewater,2020,36(18):122.
[8]孙高升,王东东,弋凡,等.淮河流域地表水类Ⅳ类标准污水深度处理工艺研究[J].中国给水排水,2020,36(19):16.
SUN Gao-sheng,WANG Dong-dong,YI Fan,et al.Advanced Wastewater Treatment Process with Effluent Quality Meeting Level Quasi Ⅳ Criteria of Surface Water in Huai River Basin[J].China Water & Wastewater,2020,36(18):16.
[9]李亮,邱宏俊.改良A2/O氧化沟强化生化处理技术用于污水厂提标改造[J].中国给水排水,2020,36(20):124.
LI Liang,QIU Hong-jun.Application of Improved A2/O Oxidation Ditch Enhanced Biochemical Treatment Process for Upgrading the Wastewater Treatment Plant[J].China Water & Wastewater,2020,36(18):124.
[10]黄志心.城镇污水处理厂提标改造实践与思考[J].中国给水排水,2020,36(22):48.
HUANG Zhi-xin.Practice and Thinking of Upgrading and Reconstruction of Municipal Wastewater Treatment Plant[J].China Water & Wastewater,2020,36(18):48.