ZHENG Feng,MU Yang,SUN Xun.MBR Process Used in Expansion Project of a Sewage Treatment Plant in Shandong Province[J].China Water & Wastewater,2020,36(18):81-84.
MBR工艺用于山东省某污水处理厂扩建工程
- Title:
- MBR Process Used in Expansion Project of a Sewage Treatment Plant in Shandong Province
- 摘要:
- 山东某污水处理厂现有设计规模为20×104 m3/d,采用氧化沟形式的AAO+纤维束过滤工艺,出水达到一级A排放标准。扩建工程规模为10×104 m3/d,占地面积4 hm2,设计出水COD≤45 mg/L、NH3-N≤2(3.5) mg/L、TP≤0.4 mg/L,其余指标需达到一级A标准。基于扩建工程占地面积小、出水标准高,设计采用预处理+AAO+MBR+紫外线消毒工艺,辅以化学除磷、投加碳源等措施,且厂区采用整体式布置,以节省占地。工程建成后,运行效果稳定,出水BOD5、COD、NH3-N、SS、TN、TP平均值分别为2.2、11.7、0.3、4.1、9.6、0.12 mg/L,均优于设计标准。
- Abstract:
- The existing design scale of a sewage treatment plant in Shandong is 20×104 m3/d, using AAO in the form of oxidation ditch + fiber bundle filtration process. The effluent reached the first class A level criteria specified in Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant(GB 18918-2002). The scale of the expansion project is 10×104 m3/d, covering an area of 4 hm2. The designed effluent COD≤45 mg/L, NH3-N≤2(3.5) mg/L, TP≤0.4 mg/L, and the other indicators should reach the first class A level of GB 18918 -2002. Based on the small footprint of the expansion project and high water discharge standards, the design adopted pretreatment+AAO+MBR+ultraviolet disinfection process, and supplemented by measures such as chemical phosphorus removal and carbon source addition. And the plant area adopted an overall layout to save land. After the project was completed, the operation effect was stable. The average values of BOD5, COD, NH3-N, SS, TN and TP of effluent water were 2.2 mg/L, 11.7 mg/L, 0.3 mg/L, 4.1 mg/L, 9.6 mg/L and 0.12 mg/L, respectively. All were better than design standards.
相似文献/References:
[1]王 亮.马来西亚Pantai地埋式污水厂环网供配电结构设计[J].中国给水排水,2018,34(22):63.
WANG Liang.Power Supply and Distribution Structure Design of Ring Network for Pantai Underground Wastewater Treatment Plantin Malaysia[J].China Water & Wastewater,2018,34(18):63.
[2]侯晓庆,邓 磊,高海英,等.MBR工艺在神定河污水处理厂升级改造工程中的应用[J].中国给水排水,2018,34(22):66.
HOU Xiao-qing,DENG Lei,GAO Hai-ying,et al.Application of MBR Process in the Upgrading and Reconstruction Project of Shending River WastewaterTreatment Plant[J].China Water & Wastewater,2018,34(18):66.
[3]邱明海.北京市垡头污水处理厂改扩建工程设计技术方案[J].中国给水排水,2018,34(20):13.
QIU Ming hai.Reconstruction and Expansion Design Technical Plan of Beijing Fatou Wastewater Treatment Plant[J].China Water & Wastewater,2018,34(18):13.
[4]郝二成,郭毅,刘伟岩,等.基于数学模拟的污水厂运行分析——建模与体检[J].中国给水排水,2020,36(15):23.
HAO Er-cheng,GUO Yi,LIU Wei-yan,et al.Operation Analysis of Wastewater Treatment Plant Based on Mathematical Simulation: Modeling and Examination[J].China Water & Wastewater,2020,36(18):23.
[5]张月,王阳,张宏伟,等.阳泉市污水处理二期工程BARDENPHO工艺设计和运行[J].中国给水排水,2020,36(16):64.
ZHANG Yue,WANG Yang,ZHANG Hong-wei,et al.Design and Operation of BARDENPHO Process in Phase Ⅱ Project of Yangquan Wastewater Treatment Plant[J].China Water & Wastewater,2020,36(18):64.
[6]祝新军,蔡芝斌,姚斌,等.绍兴污水处理厂气浮设备的优化改造[J].中国给水排水,2020,36(16):101.
ZHU Xin-jun,CAI Zhi-bin,YAO Bin,et al.Optimization and Modification of Air Floatation Equipment in Shaoxing Wastewater Treatment Plant[J].China Water & Wastewater,2020,36(18):101.
[7]王文明,杨淇椋,蔡依廷,等.MSBR工艺在高排放标准污水处理厂的应用[J].中国给水排水,2020,36(16):111.
WANG Wen-ming,YANG Qi-liang,CAI Yi-ting,et al.Application of MSBR Process in Wastewater Treatment Plant with Stringent Discharge Standard[J].China Water & Wastewater,2020,36(18):111.
[8]郝二成,郭毅,刘伟岩,等.基于数学模拟的污水厂运行分析——控制与优化[J].中国给水排水,2020,36(17):23.
HAO Er-cheng,GUO Yi,LIU Wei-yan,et al.Operation Analysis of Wastewater Treatment Plant Based on Mathematical Simulation: Control and Optimization[J].China Water & Wastewater,2020,36(18):23.
[9]王阳,张月,王晓康,等.高排放标准下的改良AAO+深度处理工程案例[J].中国给水排水,2020,36(18):56.
WANG Yang,ZHANG Yue,WANG Xiao-kang,et al.Project Case of Modified AAO and Advanced Treatment Process under High Emission Standards[J].China Water & Wastewater,2020,36(18):56.
[10]张莉,余国富,瞿露,等.重庆市某污水处理厂一级A提标改造运行效果分析[J].中国给水排水,2020,36(18):95.
ZHANG Li,YU Guo-fu,QU Lu,et al.Analysis on the Operation Effect of a WWTP Upgrading Project for the Firstlevel A Standard in Chongqing[J].China Water & Wastewater,2020,36(18):95.