FU Yao,ZHANG Li-ting.Application of Integrated Secondary Treatment and Ozonation in WWTP Upgrading and Expansion to Meet Quasi-Ⅳ Standards[J].China Water & Wastewater,2020,36(22):141-144.
一体式组合池及臭氧氧化用于污水厂准Ⅳ类提标扩建
- Title:
- Application of Integrated Secondary Treatment and Ozonation in WWTP Upgrading and Expansion to Meet Quasi-Ⅳ Standards
- Keywords:
- secondary treatment; ozonation; upgrading and expansion
- 摘要:
- 西咸新区某污水处理厂提标扩建工程设计规模为5×104 m3/d,出水水质执行《地表水环境质量标准》(GB 3838—2002)准Ⅳ类标准。该工程二级处理新增1×104 m3/d改良AAO+矩形周进周出二次沉淀一体式组合池,三级处理新建臭氧接触池及V型滤池,出水采用紫外线消毒,总投资为8 058.93万元。提标扩建工程投入运行后,出水水质稳定达到准Ⅳ类标准。
- Abstract:
- The design capacity of a wastewater treatment plant upgrading and expansion project in Xixian New Area is 5×104 m3/d, and the effluent water quality is in accordance with the quasi-Ⅳ standard of Environmental Quality Standards for Surface Water (GB 3838—2002). The integrated process including modified AAO and secondary sedimentation tank with peripheral water inlet and outlet is adopted in secondary treatment, while ozone contact tank and V-filter are newly built in tertiary treatment, and the effluent is disinfected by ultraviolet light. The total investment is 80.589 3 million yuan. After operation, the effluent quality can stably meet design standard.
相似文献/References:
[1]刘文琛,周伟伟,成小翔,等.臭氧组合技术对给水处理低压膜污染控制研究进展[J].中国给水排水,2020,36(8):44.
[2]段跟定,张胜利,吴国忠.五段Bardenpho/反硝化深床滤池/臭氧氧化处理工业园废水[J].中国给水排水,2020,36(22):116.
DUAN Gen-ding,ZHANG Sheng-li,WU Guo-zhong.Application of Five-stage Bardenpho/Denitrification Deep Bed Filter/Ozone Oxidation Process in Industrial Park Wastewater Treatment Project[J].China Water & Wastewater,2020,36(22):116.
[3]郝晓地,甘微,李季,等.臭氧降解污水厂二级出水有机物作用与效果分析[J].中国给水排水,2021,37(10):1.
HAO Xiao-di,GAN Wei,LI Ji,et al.Effectiveness of Ozonation on Oxidizing Secondary Effluent Organic Matter (EfOM) from WWTP[J].China Water & Wastewater,2021,37(22):1.
[4]高波,丁西明,康建邨,等.臭氧氧化+混凝沉淀过滤+UF+RO工艺处理矿井排水[J].中国给水排水,2021,37(10):99.
GAO Bo,DING Xi-ming,KANG Jian-cun,et al.Treatment of Mine Drainage by Ozone Oxidation+Coagulation Sedimentation and Filtration+Ultrafiltration+Reverse Osmosis Process[J].China Water & Wastewater,2021,37(22):99.
[5]马捷汀,刘新亚,马鲁铭,等.铁基催化剂整砌填料催化臭氧的运行工况研究[J].中国给水排水,2022,38(5):32.
MAJie-ting,LIUXin-ya,MALu-ming,et al.Operating Conditions of Ozonation Process Catalyzed by Iron-based Catalyst Packing[J].China Water & Wastewater,2022,38(22):32.
[6]马振坤,刘永泽,张立秋,等.微气泡强化臭氧去除污水厂二级出水中的有机物[J].中国给水排水,2024,40(5):63.
MAZhen-kun,LIUYong-ze,ZHANGLi-qiu,et al.Microbubble Enhanced Ozonation for Removing Organic Matters from Secondary Effluent[J].China Water & Wastewater,2024,40(22):63.