QILi-hua,DENGHai,TANQing-jian,et al.Key Considerations in Design of Sewage Pipelines Crossing River Project in a Coastal River Network City[J].China Water & Wastewater,2025,41(10):65-69.
滨海河网城市污水管穿越河涌工程设计关键点
- Title:
- Key Considerations in Design of Sewage Pipelines Crossing River Project in a Coastal River Network City
- Keywords:
- sewage pipeline network; crossing river project; coastal river network city; pipeline jacking technology; directional drilling technology
- 摘要:
- 珠海市境内河流众多,是典型的滨海河网城市。斗门区莲洲镇某污水管网工程范围涉及7条河涌,污水管穿越河涌建设共14处,其中5处顶管施工穿河、3处定向钻施工穿河、6处支墩架空跨河。为顺利通过防洪评价审查和政府审批,对污水管涉河建设方案中的过河埋深和两侧堤岸检查井选址等两个关键点进行讨论,综合对比分析市政行业和水利行业的多个相关技术标准及规程,在20年一遇或50年一遇的河道防洪标准下,采用InfoWorks ICM河道水力模型进行河道水位、流量、冲刷深度等水力计算,完成污水管道穿越河涌工程设计关键点分析,可以为类似项目提供参考。
- Abstract:
- Zhuhai City, a typical coastal river network city, is home to numerous rivers. The scope of a specific sewage pipeline network project in Lianzhou Town, Doumen District, encompasses seven rivers. A total of fourteen sewage pipeline crossings are involved, including five pipeline jacking constructions, three directional drilling constructions, and six overhead crossings with piers. To successfully pass the flood control evaluation review and obtain government approval, this paper discussed two critical aspects of the sewage pipeline crossing river construction plan: the river-crossing burial depth and the site selection for inspection wells on both sides of the embankment. A comprehensive comparison and analysis of multiple relevant technical standards and regulations from both the municipal and water conservancy industries was conducted. Under the river flood control standards corresponding to a 20-year or 50-year return period, the InfoWorks ICM river hydraulic model was utilized to perform hydraulic calculations, including water level, flow rate, and scouring depth of the river channel. This analysis provides key considerations in the design of sewage pipeline crossing river project, offering valuable references for similar projects.
相似文献/References:
[1]于晨晖,张梦瑶,李彭,等.基于水力模型优化污水泵站的启停水位[J].中国给水排水,2021,37(1):81.
YU Chen-hui,ZHANG Meng-yao,LI Peng,et al.Optimization of Start-Stop Water Levels of Sewage Pumping Station Based on Hydraulic Model[J].China Water & Wastewater,2021,37(10):81.
[2]张俊,尤岚,黄继会,等.泵站区域协同调度用于苏州城区污水管网低水位运行[J].中国给水排水,2021,37(4):106.
ZHANG Jun,YOU Lan,HUANG Ji-hui,et al.Application of Regional Co-scheduling of Pumping Stations in Low Water Level Operation of Suzhou Urban Sewage Pipeline Network[J].China Water & Wastewater,2021,37(10):106.
[3]汪宙峰,徐建伟,龙沁洪,等.基于GIS的污水管网易爆气体时空分布特征研究[J].中国给水排水,2021,37(15):63.
WANG Zhou-feng,XU Jian-wei,LONG Qin-hong,et al.Temporal and Spatial Distribution Characteristics of Explosive Gas in Sewage Pipe Network Based on GIS[J].China Water & Wastewater,2021,37(10):63.
[4]郭效琛,李萌,杜鹏飞,等.降雨入流入渗定量评价方法及指标的对比[J].中国给水排水,2022,38(11):133.
GUOXiao-chen,LIMeng,DUPeng-fei,et al.Comparison on Quantitative Evaluation Methods and Indexes of Rainfall Inflow and Infiltration[J].China Water & Wastewater,2022,38(10):133.
[5]任俊豪,殷伟民,贺酰淑,等.水力条件对污水管网沉积层中SRB与MA的影响[J].中国给水排水,2022,38(23):17.
RENJun-hao,YINWei-min,HEXian-shu,et al.Effect of Hydraulic Conditions on Abundance of Sulfate-reducing Bacteria and Methanogen in Sediment Layer of Sewage Pipe Network[J].China Water & Wastewater,2022,38(10):17.
[6]黄棚兰,庞晶津,陈茗,等.污水管网外水流量与入流位置的模型估算[J].中国给水排水,2023,39(5):74.
HUANGPeng-lan,PANGJing-jin,CHENMing,et al.Model Estimation of External Water Flow and Inflow Location in Sewage Pipe Network[J].China Water & Wastewater,2023,39(10):74.
[7]薛甜,石烜,赵楠,等.污水管网不同汇流条件下沉积物运移分布规律[J].中国给水排水,2023,39(7):107.
XUETian,SHIXuan,ZHAONan,et al.Migration and Distribution of Sediment in Sewage Sewer Network under Different Confluence Conditions[J].China Water & Wastewater,2023,39(10):107.
[8]石顺权,唐雨语,陈德业,等.联合调度策略用于河网区污水系统倒灌口排查[J].中国给水排水,2023,39(24):115.
SHIShun-quan,TANGYu-yu,CHENDe-ye,et al.Application of Joint Dispatching Strategy to Investigate the Backflow Points of the Sewage System in the River Network Area[J].China Water & Wastewater,2023,39(10):115.