ZENG Mu-hai,XIE Xiao-long.Application of Initial Rainwater Storage Tank in a Lake Comprehensive Treatment Project in Wuhan[J].China Water & Wastewater,2021,37(12):93-97.
初雨调蓄池在武汉市某湖泊综合整治工程中的应用
- Title:
- Application of Initial Rainwater Storage Tank in a Lake Comprehensive Treatment Project in Wuhan
- Keywords:
- initial rainwater; runoff pollution control; intelligent diversion well; combined storage tank
- 摘要:
- 武汉市某湖泊综合整治工程采用“截流—调蓄—处理”方案,通过智能分流井将初雨截流至组合式初雨调蓄池,雨后再抽排至污水处理厂处理,以削减入湖污染负荷。组合式初雨调蓄池由格栅渠、隔油沉砂池、旱流污水泵站、调蓄池及附属通风除臭系统组成,所有组成部分与调蓄池合建。格栅渠、隔油沉砂池可对初雨进行一级处理,减轻污水厂处理负荷。结合该工程的实施,介绍了智能分流井的工作原理、组合式调蓄池的设计、自冲洗系统的设计,以及调蓄容积、通风换气量和除臭风量的计算,可为初雨调蓄池的设计提供参考。
- Abstract:
- The scheme of “interception-storage-treatment” was adopted in a comprehensive treatment project of a lake in Wuhan. Initial rainwater was intercepted to the combined initial rainwater storage tank through intelligent diversion wells, and then pumped to the sewage treatment plant for treatment after the rain, so as to reduce the pollution load flowing into the lake. The combined initial rainwater storage tank consisted of grid channel, oil separation grit chamber, dry weather flow pumping station, storage tank, adjunctive ventilation and odor control system, and all the components were constructed in conjunction with the storage tank. Grid channel and oil separation grit chamber could be used for pretreatment of initial rain to reduce the load of sewage treatment plant. Based on the implementation of the project, working principle of intelligent diversion well, design of combined storage tank and self-washing system and calculation of storage capacity, ventilation flow rate and deodorization air volume were introduced, which can provide reference for the design of the initial rainwater storage tank.
相似文献/References:
[1]徐晓明,杨国洪,刘楷操.清污分流渠在珠海市黑臭水体整治中的应用[J].中国给水排水,2020,36(10):113.
[2]赵也,汤钟,曾胜.基于模型评估的黑臭水体综合治理方案目标可达性分析[J].中国给水排水,2020,36(13):73.
ZHAO Ye,TANG Zhong,ZENG Sheng. Objective Reachability Analysis of Comprehensive Treatment Scheme of Black and Odorous Water Body Based on Model Evaluation [J].China Water & Wastewater,2020,36(12):73.
[3]杜家慧,薛祥山,邹蓉,等.具有高原阶梯型坡地特点的海绵城市设计案例[J].中国给水排水,2020,36(16):30.
DU Jia-hui,XUE Xiang-shan,ZOU Rong,et al.Case Design of Sponge City with the Characteristics of Plateau Slope[J].China Water & Wastewater,2020,36(12):30.
[4]笪健,王德生,曹兴坤,等.潍坊市超大型调蓄池工艺设计与建设特点[J].中国给水排水,2020,36(18):85.
DA Jian,WANG De-sheng,CAO Xing-kun,et al.Process Design and Construction Characteristics of Super Large Storage Tank in Weifang City[J].China Water & Wastewater,2020,36(12):85.
[5]史昊然.合流制溢流调蓄处理工艺效果评估及优化对策[J].中国给水排水,2021,37(5):106.
SHI Hao-ran.Performance Evaluation and Optimization Solutions of Combined Sewer Overflow Storage and Treatment Process[J].China Water & Wastewater,2021,37(12):106.
[6]周传庭,朱砂砾,杨殿海,等.初期雨水就地快速处理技术中试研究[J].中国给水排水,2022,38(19):108.
ZHOUChuan-ting,ZHUSha-li,YANGDian-hai,et al.Pilot Study on On-site Rapid Treatment Technology of Initial Rainwater[J].China Water & Wastewater,2022,38(12):108.
[7]钟江丽,沈捷,高华,等.基于DOM荧光光谱分析的初期雨水径流污染物溯源[J].中国给水排水,2023,39(7):133.
ZHONGJiang-li,SHEN Jie,GAOHua,et al.Source Tracing of Initial Rainwater Runoff Pollutants Based on DOM Fluorescence Spectrum Analysis[J].China Water & Wastewater,2023,39(12):133.
[8]侯文硕,周国华,葛铜岗,等.新型容积-流量型雨水弃流装置设计及效果评估[J].中国给水排水,2023,39(9):103.
HOUWen-shuo,ZHOUGuo-hua,GETong-gang,et al.Design and Effect Evaluation of a New Volume-Runoff Stormwater Diverting Device[J].China Water & Wastewater,2023,39(12):103.